Development update — highlights from Calcalit Lod's Q2 2026 board report

Published on 27 July 2026

Below is a summary of the International Quarter highlights from the Lod Economic Company’s Q2 2026 board presentation (an official document published by the company). This is our summary — for the full document and exact figures, see the official report.

Infrastructure

  • Pumping station — under construction, completion planned for Q4 2026.
  • Road 200 pressure lines — works completed.
  • Infrastructure works — stage A done; stage C expected to finish in August; overall completion planned for Q3 2026.
  • Tzafria reservoir — planning completed; conduit laying planned for Q2 2027.
  • Water lines, drainage lines, and road paving are underway on site.

Electricity

  • Transformer rooms — planning with the Israel Electric Corporation (IEC) completed; 4 rooms placed, energization planned for Q4 2026.
  • Electricity connection — the IEC began works in Q2 2026; completion of IEC works in complexes A+C is planned for Q1 2027.

Public buildings, schools and kindergartens

The report details many public-building plots at various planning and construction stages, including:

  • Elementary school, 18 classrooms + sports hall (plot 4011) — under construction, completion planned for Q4 2027.
  • Elementary school, 24 classrooms + mikveh (plot 4014) — in detailed design.
  • Kindergartens, daycares and synagogues — several plots (4021, 4008, 4023, 4010 and more) in planning and construction, with start/completion dates spread across 2026–2027.

Marketing

According to the report, the International Quarter is planned for about 6,710 housing units, of which roughly 4,500 are being marketed in 2025–2027.


The above is a summary of an official Lod Economic Company document, for general reference; dates and scope may change. For full, up-to-date information see the full report and the Lod Economic Company site.